Gross units across 8,128 issued and phased building permits, plus 65,064 units in active review.
Seattle housing, land use, and construction permits
Real permit counts, housing unit pipelines, and review timelines sourced directly from Seattle Department of Construction and Inspections open data. Snapshot verified Nov 25, 2026 (permits through Nov 23, 2026).
2026 YTD mean (58.5d median), -21% vs 2024 peak. Multifamily averages 232.2 days.
2026 YTD median (-22% vs 10-yr norm). Multifamily MUPs average 404.9 days (318d median).
Issued YTD compared with 10,814 ten-year annual average (2016 to 2025), -59%.
Typical permit timelines by building type
Median and average calendar days calculated across 72,319 issued building permits and 6,445 land use permits (2016 to 2026).
Single Family Home Standalone + Townhomes
45,256 issued permits (2016 to 2026): 40 days median (106d avg) building review, 296 days median (354d avg) construction, 245 days median (356d avg) Land Use MUP if subdivision required.
Multifamily Home / Apartment buildings
8,274 issued permits (2016 to 2026): 155 days median (232d avg) building review, 318 days median (405d avg) Land Use MUP, 409 days median (468d avg) construction.
Business buildings
15,023 commercial and 742 industrial permits (2016 to 2026): 46 days median (96d avg) commercial review, 169 days median (272d avg) build-out, 356 days median (532d avg) ground-up Land Use MUP.
Historical housing and permit production
Track annual permit volume, housing units added versus removed, and estimated construction valuation from 2014 through 2026 against the 10-year historical average.
Historical benchmarks (2014 to 2026)
Full-year averages exclude 2026 year-to-date partial totals so historical baselines stay comparable.
| Metric | 10-yr avg (16 to 25) | Peak year | 2025 full yr | 2026 YTD |
|---|---|---|---|---|
| Housing units issued (Building) | 10,814 | 16,123 (2021) | 8,972 | 4,442 |
| Housing units applied (Building) | 13,517 | 22,916 (2020) | 5,543 | 3,587 |
| Building permits issued | 6,866 | 8,051 (2017) | 6,334 | 5,814 |
| Building valuation issued | $4.52B | $6.85B (2025) | $6.85B | $4.21B |
| Land Use MUP units applied | 8,293 | 14,667 (2015) | 3,044 | 927 |
| Trade permits issued | 17,064 | 20,841 (2023) | 18,952 | 16,953 |
Housing category mix (2020 to 2026)
SDCI housing typology assigned to building permit applications filed since 2020, with plain-English definitions.
Permit review and construction timelines
Exact mean, median, and upper-quartile calendar durations calculated across 72,319 issued building permits and 6,445 land use permits from 2016 through 2026.
Turnaround by permit class
Median dot, mean marker, and 75th to 90th percentile range in calendar days (2016 to 2026).
Multifamily entitlement to occupancy
Typical calendar time across major permitting and build stages for Seattle multifamily housing.
Note: Developers often file building permit applications before final Master Use Permit issuance, so combined end-to-end timelines can overlap by 2 to 6 months.
Active housing pipeline and major developments
Breakdown of open non-terminal permits by current SDCI review stage, paired with the largest active housing projects across the city.
| Address and permit | Class | Status | Housing units | Est. cost | Applied / Issued |
|---|
Where Seattle housing is being built
Spatial distribution of the top 200 active housing permit sites and total active units by Seattle ZIP code. Select a neighborhood to highlight its permits on the map.
Active housing units by ZIP code
Active non-terminal building permits with housing units added. Click a row to isolate that ZIP on the map.
Seattle Open Data APIs and methodology
All figures query the City of Seattle Socrata Open Data API directly from the browser (CORS enabled). Run live queries or inspect the accounting methodology below.
Connected SDCI Socrata datasets
Live API query runner
Optional Socrata App Token raises anonymous rate limits. Leave blank for standard public queries.
| Permit | Address | Class / Stage | Units | Date |
|---|
Data methodology and known nuances
Mean versus median turnaround times
Permit review durations are heavily right-skewed: simple over-the-counter permits clear in days while stalled or appealed multifamily towers can take years. Both mean and median (plus 75th and 90th percentiles) are reported side by side. Negative date artifacts (13 of 72,332 records) are excluded.
Site-level multi-permit unit accounting
SDCI frequently attaches a development site's proposed housingunitsadded to paired demolition (-DM), shoring, and phased construction (-PH) permits. Active review totals reflect raw SDCI permit rows; the major developments table defaults to building permits only to reduce double counting.
2026 year-to-date completion bias
Construction duration (issued to completed) for permits issued in 2026 (104.8d mean) only reflects fast-finishing projects already completed within the same calendar year. Use 2016 to 2023 cohorts for unbiased construction duration benchmarks.
SoQL date type handling
Building Permits (76t5-zqzr) stores dates as floating timestamps, whereas Land Use Permits (ht3q-kdvx) and Trade Permits (c87v-5hwh) store YYYY-MM-DD strings requiring explicit ::floating_timestamp casts in live SoQL queries.